Questions & Answers
What are Asphalt’s Advantages?
by Dwight Walker
(Courtesy of the Asphalt Institute and the Asphalt Pavement Alliance)
Ninety-four percent of U.S. roads (and roads in Hawaii) are surfaced with asphalt, and there are about 18 billion tons of asphalt in place on our roads. There must be a reason for such wide spread usage. Actually, there are many reasons. It is my opinion that asphalt is truly the most adaptable and versatile paving material. Here are some of the reasons for using asphalt.
Versatility/adaptability
Asphalt is a marvelous engineering material. It lends itself to working in a great number of applications. It can be a load-carrying or structural component; it can be a wearing course or a waterproofing layer. It can be extremely dense or free-draining. It can be placed in thick layers to last indefinitely or it can be placed in ultra-thin overlays to preserve an existing road.
Recyclable/reusable/rejuvenation
Asphalt can be and is re-used. RAP or recycled asphalt pavement has incredible value. Nearly 100 million tons of asphalt is re-used each year. The aggregate component of RAP saves resources and the asphalt can be restored to approximately its net original properties by using a compensating binder with the recovered materials. Other pavement types can only be re-used as an aggregate.
In addition to re-using RAP, asphalt mixtures routinely incorporate other scrap or waste materials, such as tire rubber, roofing shingles, glass, and other materials. An asphalt pavement can, effectively, recycle concrete through the rubblization process. Failed concrete pavements are broken down in-place and used as an aggregate base for a new asphalt pavement. This technique offers the environmental advantages of conserving aggregate and saving landfill space.
Speed of construction
Asphalt is quick to place and requires less traffic delays due to congestion or lanes being out of service. Much of the work can be done during off-peak hours, and this saves the traveling public time and money. Asphalt pavements can be opened to traffic as soon as they are compacted and cooled, while other pavement types can take days or even weeks to cure.
Quiet
Asphalt pavements are quieter than other pavement types. Some asphalt mix types (OGFCs and SMAs) typically reduce noise levels by three to five decibels, which is like doubling the distance from the source of the noise. Noise barrier walls are incredibly expensive and paving with asphalt is the better choice.
Smooth
Asphalt pavements are undeniably smoother. Because asphalt is smoother, some agencies hold asphalt to higher smoothness specs. The public appreciates a smooth ride, and as an added benefit, vehicles get better fuel mileage on smooth pavements.
Perpetual Pavements
These pavements are designed so that only the top, surface layer is renewed on a 15-year or longer cycle. The base, structural layers last indefinitely (40 years or more); hence, the name perpetual pavements. Over their lifetime, these pavements use less materials and have a lower overall life cycle cost.
Readily repaired
If needed, asphalt can be readily repaired. These repairs can be done during off-peak travel times, often over-night, while other pavement types may require weeks for repairs or replacement.
Warm mix asphalt
New technologies have allowed asphalt mixtures to be mixed and placed at significantly lower temperatures. A 50-degree F reduction is typical and 100-degree is possible. The warm mix processes (there are numerous methodologies) save burner fuel and reduce emissions. Other observed benefits may include easier compaction, extended haul distances and/or paving seasons and higher RAP contents.
Porous pavements
Asphalt mixtures can be designed to be free-draining. Such engineered installations can be used in storm-water management. The filtering process of these installations can improve the water quality by removing contaminants during the retention time.
Safety
Specially designed asphalt mixtures, such as Open Graded Friction Courses (OGFCs), can allow water to travel through the pavement surface layer and away from the actual riding surface. This reduces spray, decreases hydroplaning and increases skidding resistance.
Life cycle cost
At one time, asphalt had a significantly lower initial cost than other pavement types. This may not always be the case today, but asphalt stills remains the lowest overall cost paving material. When alternate bids are received, asphalt routinely wins.
Familiarity
I started off saying that 94 percent of our roads have asphalt surfaces. With that much volume, it is not a problem to find a qualified, competent contractor. They are out there working every day to build and preserve our roads.
With all these advantages, it is easy to see that asphalt is the obvious choice.
ASTM versus AASHTO Standards - What's the difference?
by Brian J. Johnson, AASHTO Accreditation Program Director, AASHTO re:source
ASTM and AASHTO are two separate entities that serve slightly different purposes with different members making decisions even though they both end up at about the same place
ASTM is primarily a standards development organization that operates in just about every industry. Construction materials is just one of them. ASTM membership is voluntary with members from all over the world and with varying levels of expertise and roles in their industries, which contributes to a broad collective perspective. Anyone can vote on the electronic ballots, but most of the effort maintaining the standards comes from those who attend the meetings in person (at least in construction materials).
Those members are mainly materials producers, testing firms, equipment manufacturers, consultants, researchers, governmental agencies, accreditation bodies, certification programs, calibration providers, and other interested parties. These members drive forward changes in practices, test methods, and specifications to keep up with improvements in equipment, quality concepts, and techniques.
AASHTO serves many roles in the transportation industry, and one is as a standards development organization for the state departments of transportation (DOTs). State DOTs work together on maintaining this set of standards through AASHTO’s Committee on Materials and Pavements (COMP) that all states can use instead of maintaining their own set of standards in their states.
The members of COMP are usually state materials engineers. Anyone can comment or suggest changes to AASHTO standards, but it takes a member to drive it forward, and only members have voting rights. However, some of the same members from corresponding ASTM committees contribute to ballots and discussions in COMP so the perspective is not as narrow as it sounds based on the limitation of membership, but ultimately only the DOTs are deciding on whether a change is going to be made in an AASHTO standard. COMP also serves a unique role in the standards development arena because it evaluates research proposals that leads to the advancement of technologies that often are the basis for new or revised standards.
I mentioned that they end up at about the same place, but there are significant efforts going on to harmonize the AASHTO and ASTM standards so that the most common standards are identical. Also, new standards can now only be published by either ASTM or AASHTO according to an agreement between the two organizations. That helps reduce the proliferation of more standards that are not quite the same covering the same type of test.
What I would really like to see is one super-committee in which the interests of the DOTs, industry, and other interested parties are working on the same exact standard together, and then everyone could just use that standard…but like I said, ASTM covers just about every industry, and this would be a rather significant change to their operations to accommodate one industry. It would also cause a change in the policies, balloting system, and membership management for COMP – so even though it sounds like it might be easy to do, it would be quite a massive undertaking for both organizations.
If you would like to read more about this topic, you can check out these newsletter articles: The Birth of a Standard – Part I: Who Are AASHTO and ASTM? and The Birth of a Standard – Part II: The Harmonization Effort.
Who Can Fix a Pothole?
For public roads, the pothole would be repaired by the agency that owns the road:
The City has a Pothole Hotline: https://www.honolulu.gov/dfm/pothole.html. Phone numbers for the State and HART pothole hotline can be found at that site, as well as a listing of roads under State or HART jurisdiction.
Potholes within HART work areas can be reported directly to HART at info@honolulutransit.org or the City’s pothole reporting . HART’s contractors routinely repair portholes during construction.
The County of Hawaii has a website for reporting problems such as potholes.
https://www.dpw.hawaiicounty.gov/divisions/highway-maintenance/report-problems
Cold-mix asphalt is a mixture of asphalt and a solvent and/or water, aggregates, reclaimed asphalt pavement (RAP) and other minerals typically used for patching and for repair of small sections of pavement. The asphalt and solvent portion, excluding the other components of the cold mixture, is often referred to as “cutback asphalt.” Evaporation, or curing, of these components – solvents and/or water – in a cold-mix asphalt leads to the hardening of the asphalt mixture. I assumed Asphalt emulsions also require the evaporation of water and a relatively short “cure time.” However, it is not common or appropriate to refer to these products as “asphalt” without including some type of additional descriptors, such as “cold-mix”, “cutback”, or “emulsion.” When the word “asphalt” is used without a descriptor, it is most commonly referring to an “asphalt mixture”, which includes the heated liquid asphalt and aggregates that are compacted to build a typical roadway; otherwise, the term “asphalt” may be referring solely to the hot liquid asphalt portion of the mixture. “Hot-mix asphalt” is a term often used to refer to an asphalt mixture, and “warm-mix asphalt” may also be used to describe an asphalt mixture that is either processed with an additional additive or using foaming techniques that allow the temperature of the mixture to be reduced slightly, although the mixture is still very hot. Simple answer Asphalt is liquified by applying external heat, which allows it to be mixed, transported and compacted and the mixture rapidly hardens as heat dissipates and achieves full strength upon cooling to ambient temperature. Therefore, I want to make this as clear as possible – asphalt, which is the material used to build 94 percent of our roadway infrastructure in the U.S., does NOT have a cure time. Asphalt begins to cool immediately after mixing and cooling continues during transport, construction and post-construction. It will typically gain full strength and can support traffic within minutes after construction but can take hours in rare cases, depending on lift-thickness, ambient conditions and other variables. Complex answer For the more technical readers, there are two key temperature ranges that should be considered to ensure that asphalt construction operations cease and traffic operations commence at the proper times: 1. Cessation temperature (internal asphalt temperature in which all construction operations must cease to prevent damage caused by construction equipment) 2. Maximum ambient temperature (internal asphalt temperature below which a newly constructed asphalt pavement has cooled sufficiently to be trafficked without causing premature damage) The internal portion of an asphalt pavement during construction and immediately post-construction may be slower to cool than the surface. This effect can be much more pronounced for pavement lifts thicker than two inches, so internal temperature may be temporarily higher than surface temperature until equilibrium is reached. For pavement lifts two inches and thinner, the surface temperature is a more reasonable approximation of internal temperature during the cooling phase. Asphalt Institute’s MS-22 “Construction of Quality Asphalt Pavements” says the following about cessation temperature: “Compaction should be completed before the internal mix temperature falls below what is referred to cessation temperature, typically around 175-180°F (80-82°C). The cessation temperature will vary from project to project. Therefore, it is important to establish a target cessation temperature at the beginning of each project.” Once an asphalt pavement has cooled to ambient temperature, surface temperature will closely trend with ambient air temperature, but due to the effects of surface heat radiation, pavement temperature is typically greater than the ambient air temperature. For example, if it is 90°F outside, the pavement surface may be up to 120°F or greater, depending on UV intensity and other factors. The precise post-construction maximum pavement temperature permitted for traffic opening will differ based on the climate and materials selected for construction. Choosing a binder Performance-graded asphalt binders are selected based on a design maximum pavement temperature 20 mm below the pavement surface. This design value is dependent on a maximum air temperature and the geographical latitude for a given region. For example, there is more than 99 percent reliability that a pavement temperature will not exceed 136.4°F (58°C) in Cleveland, Ohio. Therefore, a pavement constructed with a PG 58-28 grade binder in Cleveland, Ohio would be ready to open to traffic once the internal pavement temperature post-construction has cooled below the maximum design temperature of 136.4°F (58°C). In a hotter climate, An asphalt grade that can support traffic at a temperature up to 76°C (168.8°F) means that a newly built roadway should be able to open to traffic very shortly after final roller pass occurs between 175-180°F. This matches closely with the language shown in the Florida Department of Transportation’s (FDOT’s) Specification Section 330-10: “To prevent rutting or other distortion, protect sections of newly finished dense-graded friction course and the last structural layer before friction course from traffic until the surface temperature has cooled below 160°F.” The specification then goes on to say the contractor may use artificial methods to cool the pavement and may be directed to do so when it is desirable to open the pavement at the earliest possible time. Therefore, the required time to open a newly constructed two-inch asphalt surface to traffic would generally be just a few minutes. Thicker lifts will take longer to cool internally, and in rarer cases of asphalt construction, it could take hours. DOT and airfield project engineers or other representatives present at the construction site may give the order when an asphalt pavement is ready to be opened to traffic. The lack of a cure time for asphalt, or its speed of construction, is one of the unique advantages of using asphalt as the primary roadway and airfield building material and an attribute which makes it uniquely different than portland cement concrete (PCC). The load-bearing capacity of PCC is normally measured and estimated according to its compressive strength over a slow curing time. A typical strength-gain curve for PCC is: • 1-day: 16% Honest question Back to my engineering colleague who asked, “what is the cure time for asphalt?” to which I responded, “are you referring to cold-mix asphalt?” He responded: “no; I’m referring to hot-mix asphalt.” Now, let me provide a little more background on my engineer colleague. He’s no rookie. He’s a very accomplished engineering professional. His engineering career has mostly encompassed working with structures, including concrete mix design, concrete construction, blast testing, blast mitigation, etc., and he’s been practicing engineering for over 30 years. He will soon retire. When he clarified his question, one thing occurred to me. If a structural engineer with decades of experience does not understand that asphalt does NOT “cure”, there must be an abundance of other individuals involved in public service, infrastructure project planning, construction, design, life cycle analysis, infrastructure safety planning, user-delay analysis, etc. who also do not understand this. At this point in the article, you already have more background about asphalt strength-gain than my engineer colleague with over three decades of engineering experience. That is the primary reason I felt compelled to write this one. Misinformation I wanted to better understand where he and others might be getting their information about asphalt, so I went to the Google search bar and typed in “What is the cure time for asphalt?” The results, which you can verify for yourself, were very disappointing. Nearly every search result, including the following examples, falsely indicates there is a cure time associated with asphalt construction: • “6-12 months” Almost none of the information returned in the Google search accurately answers the precise question my colleague asked, which I admit, was quite surprising to me. At best, the information is extremely misleading, and at worst, it results in the implementation of poor infrastructure policy based on a misunderstanding of how asphalt gains strength after placement. Now I understand why my colleague was confused about how asphalt hardens and why just about anyone else outside of the asphalt industry might be also. I learned a couple of lessons in this case –don’t assume what others might know and understand, and always verify the information found on the internet. If you have any asphalt-related questions, please do like my engineer colleague, and come to a trusted source of information, such as the Asphalt Institute. We can’t eliminate misleading information on the internet, but we can provide accurate answers to questions like this, and even much tougher questions presented by practitioners, engineers, the general public, those interested in transportation and particularly those involved in making important transportation investment decisions impacting billions of dollars in infrastructure funding. Allen is an Asphalt Institute Regional Engineer based in Florida. Click here for a PDF file of the magazine article. The answer to question is not a straightforward material cost comparison between porous asphalt and dense graded asphalt. To compare the two asphalt types, a cost study should be done to include the entire pavement section. The materials used beneath a porous asphalt and a dense graded asphalt are quite different. The other major cost item to consider is that the use of a porous asphalt pavement with a stone reservoir eliminates the need for a drainage system, other than provisions for an overflow system. Therefore, the costs to compare are a porous asphalt pavement section with an overflow system versus and dense graded pavement section with an underground drainage system. Lastly, it is also important to consider:What is the Cure Time for Asphalt?
by Dr. Grover Allen, Ph.D., P.E.
(Courtesy of the Asphalt Institute)
this was likely what my colleague was referencing with his question. Another thought occurred to me that he may be referring to an asphalt emulsion, which is an aqueous solution containing tiny droplets of suspended asphalt meant to be applied in ultra-thin layers on or within a pavement structure.
such as my home state of Florida, a stiffer grade of asphalt, such as PG 76-22, is commonly specified.
• 3-day: 40%
• 7-day: 65%
• 14-day: 90%
• 28-day: 99%
• “It can take up to a full year for asphalt
to cure, but within 30 days asphalt is
cured to a point it can be driven on”
• “48-72 hours to dry completely”
• “Asphalt takes six to twelve months to fully cure and remains a little more susceptible to damage for that time”
• “The drying process happens in phases. Your asphalt may look and feel dry, but a complete curing typically takes much longer than three days.”How Much Does Porous Asphalt Cost?
How Much Does Warm Mix Asphalt Cost?