Pavement Management

"Pavement management" refers to a systematic process of maintaining, upgrading and operating a network of pavements and involves three major components: the pavement life cycle, the costs associated with this life cycle and pavement management systems.

Pavement Life Cycle

All pavement will deteriorate over time. Typically, pavement deteriorates at an ever-increasing rate: at first very few distresses are present and the pavement stays in relatively good condition, but as it ages more distresses develop with each distress making it easier for subsequent distresses to develop. For instance, once a substantial crack occurs it is then easier for water to (1) infiltrate the HMA layer and (2) penetrate and weaken the subgrade.

Maintenance and rehabilitation are the two principal treatments used to extend pavement life. These treatments will (1) immediately increase the pavement condition and (2) affect the future rate of deterioration. In general, maintenance can slow the rate of deterioration by correcting small pavement defects before they can worsen and contribute to further defects. Beyond a certain point, however, defects become too large for correction by mere maintenance. At this point, rehabilitation can be used to effect a wholesale correction of a large number of relatively severe defects, which provides a step increase in pavement condition. Figure 1 illustrates this concept.

Figure 1: Pavement Condition Illustration

Life Cycle Cost Analysis (LCCA)

All new construction, reconstruction, rehabilitation and maintenance projects should employ some level of economic evaluation to determine the most cost effective method and timing. For instance, a rehabilitation that involves placing an SMA wearing course may cost as much as 20 percent more than a typical dense-graded HMA wearing course. However, the SMA wearing course may provide up to 40 percent additional pavement life based on its rut-resistant nature.

Life cycle cost analysis is typically done over a fixed period - often 20, 40 or even 50 years. The costs normally considered are:

These costs are usually summarized over time by discounting all costs that occur at different times using the present worth method to account for the time value of money. The comparative costs may be shown as either total present worth or an annualized cost. LCCA, the availability of funds, project specific and environmental conditions or constraints, project constructability and the ability of each alternative to serve the anticipated traffic volumes should all be used in the decision process for selecting the most appropriate alternative.

For more information concerning life cycle cost analysis, refer to FHWA report FHWA-SA-98-079, Life-Cycle Cost Analysis in Pavement Design (written by Walls and Smith).

Pavement Management Systems

A pavement management system is a set of tools or methods that assist decision makers in determining cost effective strategies for maintaining, upgrading and operating a network of pavements. There are numerous different pavement management systems (PMS) from which to choose, each one with its own level of complexity. For a small town or rural county a simple system based on visual inspection and maintained in a Microsoft Excel or Access database may be more than sufficient. For a state road network a more complex PMS is usually appropriate.